- BRIEFING
- Mongolia Resort
- 1st October 2025
- Meeting with Stephen and Siow Pai
- Present situation
Nomin company set up done? Done since august 2025. - Local Mongolia Construction and Design company selected ? 3-4 company to compare
- China supplier selected? Jenny is looking for it
- ACM design – progress of design presentation? Since Pablo selected second land we need to restart prepared new drawing in which timeline is 1 month to complete
Pablo saw our design yet? Agreed ? Pablo saw but not in detail. - Pablo proposed solar panel to be more eco friendly.
- 1.03- have the land location finalized?
- Yes
- 1.05- have the design finalized ? Layout is ok with Pablo
- Sub structures work carry by local Mongolia contractor ? Yes
- But Mongolia contractor don’t work from end of October till mid of March due to winter
- Interior and tent by china suppliers ? Mongolia tent to be made in Mongolia only loose item from china
- 1.06- operation hiring
- When to start hiring staff? April or May 2026
- 1.07- Organization chart
- Please come out with this to ensure monthly overhead [ doing now and can complete within a week ]
- 1.08- marketting strategies
- Multi media marketting
Travel agent JV [ 30% ] but Pablo said is too high so this need to be negotiated - 1.10 – phase 2,3,4,5 and 6
- Need to explained fund incoming and for future expansion
- Summary of meeting is
- Winter break from end of October to mid of March is basically study and procurement works only.
- Mid of March 2026 till end of September 2026 is the actual construction periods and planning for soft opening for business on early October 2026.
- Remaining fund for this development to be ready in Mongolia only mid of march 2026.
REQUIREMENTS
Proposal:
. Layout Plan
. 3d Visualization
RESOURCES